FAQ

Penalties under RERA across states

By
3352

  • Share on
rera-penalty

In a bid to expedite the registration of realty projects under RERA, Maharashtra and Uttar Pradesh have imposed several penalties on developers who failed to list their projects with the state’s regulator. 99acres.com takes a closer look at the action that will be taken against defaulters who flout the norms.

All developers, builders and brokers and ongoing realty projects were mandated to register with the real estate regulatory authority until July 31, according to Real Estate (Regulation and Development) Act (RERA) 2016 rules.

However, while several developers rushed to register within the stipulated time, many failed to meet the deadline. Some of the States are delayed in launching their websites for project registration.

Taking cognizance of the situation, several states including Uttar Pradesh, Gujarat and Maharashtra have decided to tighten the noose on defaulters and announced a penalty clause for late registration. Although the penalties are not too high initially, the government will take strict action in future if developers fail to register within the extension provided.

Here are the list of penalties imposed by different states:

Goa

The Goa Real Estate Regulatory Authority (Goa RERA) has started imposing a penalty on developers registering their ongoing projects with the Authority under the Real Estate (Regulation and Development) Act (RERA). All builders have to pay Rs 2 lakh as the penalty while registering their projects on the RERA portal until July 1, 2018. Before this, the Authority had imposed a sum of Rs 1 lakh as the penalty for developers registering their projects till April 30, 2018.

It is to be noted that the Authority had set the deadline for project registration till March 23, 2018 without any penalty. It was found that most of the developers did not register themselves and their respective projects with the regulatory authority within the stipulated time. Considering this, the Authority had first imposed a fine of Rs 50,000 for such errant developers till March 31, 2018.

Gujarat

The Gujarat Real Estate Regulatory Authority (Gujarat RERA) has now revised the penalty charges for developers registering their ongoing realty projects under the Real Estate (Regulation and Development) Act (RERA) post-December 31, 2017. The penalty has been raised to 2.5 times the registration fee for the properties registering under the Act. 

Earlier, the state regulatory authority had raised the penalty to twice the registration fee for the properties registering their ongoing projects under the Act from November 30 till December 31, 2017.

The Gujarat RERA had decided to impose penalty charges for developers registering their ongoing projects under the Act post October 1. A fine equivalent to the registration fee for the properties was charged on projects registering between October 1 and 31. However, no penalty was charged for developers registering their projects till September 30.

Rajasthan

The Rajasthan Real Estate Regulatory Authority (Rajasthan RERA) has raised the penalty on non-registration of real estate projects with RERA from 2 percent to 10 percent. The new penalty norm is applicable from October 1 onwards.

Earlier, the Authority had imposed two percent of the project cost or 10 times the registration fee, whichever is higher, as penalty for developers registering their projects post August 31 till September 30, 2017. 

Maharashtra

The Maharashtra Real Estate Regulatory Authority (MahaRERA) has decided to double the penalty charges for developers registering their ongoing projects under the Real Estate (Regulation and Development) Act (RERA) between September 1 and September 30. A penalty amounting to Rs 2 lakh or an amount equivalent to double the registration fee, whichever is higher, would be levied on applications received during this period.

Earlier, MahaRERA had announced a penalty of Rs 1 lakh or an amount equivalent to the registration fee, whichever is higher, for projects' applications received from August 16 till August 31.

The state regulator has registered about 13,000 ongoing projects till date. Apart from projects, over 10,000 agents have been granted with RERA certificates.

Uttar Pradesh

The Uttar Pradesh government had already extended the deadline for project registration until August 15, 2017. The State government imposed the fine on developers registering their projects from August 16 onwards.

  • Developers registering their projects till August 31, 2017 were liable to pay a penalty of one percent of the overall project cost.
  • If a developer fails to register his project with UP RERA post August 31, then he was charged five percent of project cost as penalty till September 15, 2017.
  • A higher fine of 10 percent was imposed on builders registering with the authority in between September 16-30, 2017.

Karnataka

The Karnataka government has imposed a penalty of Rs 10,000 per day for agents or up to 10 percent of the cost of the project or a three years of imprisonment for builders/agents selling or advertising projects without RERA registration.

It should be noted that the Goa government had given an extension of three months to builders to register their ongoing projects under RERA. Following this, the Telangana government is also considering to extend the registration deadline for another 2-3 months.

  • Share on
Rate it 1 Star2 Stars3 Stars4 Stars5 Stars (2 votes, average: 3.00 out of 5)
Loading...Loading...
  • Comments
  • Mayuresh September 28, 20177:40 pm

    Very good & informative Article. thank you for posting.

    Reply
  • Post a New Comment

Usage of 99acres.com to upload content which enables targeting by religion/community/caste/race is prohibited. Please report inappropriate content by writing to us at report abuse
Home Legal Sitemap Send Feedback
Back To Top